| Action |
Date |
| Orientation of Leadership Team |
January 30, 2007 |
| Compliance Certification Due |
March 15, 2008 |
| Off-Site Peer Review |
May 16-20, 2008 |
| Off-Site Review Report |
May 30, 2008 |
| Focused Report Submitted |
6 weeks prior to on-site review |
| Quality Enhancement Plan (QEP) Submitted |
6 weeks prior to on-site review |
| On-site Peer Review |
September 19 - October 28, 2008 |
| Review by Commission on Colleges |
June 20-22, 2009 |
| Announcement of Reaffirmation Decision |